Licence number: 394
Annual Return Start: 18 Nov 2012
Annual Return End: 17 Nov 2013
Date Received: 17 Jan 2014
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2.2 Not all samples collected at Monitoring Point 15 due to equipment programing error. A checklist was developed to ensure systematic programming of the HVAS equipment. Appropriate Action taken by licensee 1
M2.3 Not all weekly grab samples collected from EPL Id’s 6 and 19 due to discontinuous, irregular discharge and lack of discharge. A condition monitoring system will be developed and implemented and site specific field note instructions were implemented. Non-compliance(s) under investigation 2
L2.5 Exceedence of water quality at MP no. 18 due to heavy rainfall and water discharge exceeded at MP no. 19 due to a fault occurring in the automation network system. PRP issued by EPA in response. PRP to address non-compliance(s) issued 2